Niven & Mt. Elba Rds. Overlay



City: Rison
* City Population: 1,344
County: Cleveland
Project Status: Complete
Request Date: February 27, 2013
On-Site Assessment Date: April 09, 2013
Approval Date: June 13, 2013
Approved Amount: $225,000.00
Project Length (Miles): 1.52
Job Number: C76001
Total Contract Length (Miles): 2.2
Contract Name: Fordyce & Rison Overlay (Sel. Secs.) (S)
Letting Date: September 11, 2013
Contractor: Jet Asphalt & Rock Co., Inc.
Amount of Contract: 207753.73